Rain Barrel Project: holding but not finished
From 6/23 - 6/28 we received 6 - 8" of rain. The downspouts, barrels and overflow worked as designed. I did notice some water dripping from behind the gutters at several places which will probably involve a call to JA who just installed them.
Tasks remaining:
- Seal the overflow port
- Install fence boards (already purchased)
- Install some 4x4 timber to retain gravel
- Finish and install the filter/screen bucket
- Cover each barrel tightly with mosquito proof screen and secure w/ bungee chord